Mike Fasano
stated on October 11, 2011 in a news article:
"Just a little over 60 percent of your electric bill, my electric bill, 60 percent of that is pass-throughs, whether they be for building of nuclear plants or whatever they may be." A planned nuclear plant repair "will only increase that percentage."
true mostly-true
Becky Bowers
By Becky Bowers October 18, 2011

Sen. Mike Fasano says most of your Progress Energy Florida power bill is pass-throughs

Progress Energy Florida may ask that its customers foot the bill for the physical repairs to a nuclear plant that will be offline years longer than expected.

That has state Sen. Mike Fasano, R-New Port Richey, upset. Fasano, who regularly argues on behalf of  "the little guy or gal," recently told St. Petersburg Times that he was concerned the latest $2.5 billion repair price tag -- which includes paying for the fuel to replace the energy generated by the nuclear plant -- would overburden the company's Tampa Bay and Central Florida ratepayers.

To hammer home the point, Fasano offered an interesting detail about the power bill Progress Energy customers pay each month.

"Already, just a little over 60 percent of your electric bill, my electric bill, 60 percent of that is pass-throughs, whether they be for building of nuclear plants or whatever they may be," Fasano said. "This (repair) will only increase that percentage."

This fact-check will address two points. First, does 60 percent of a Progress Energy customer's bill pay for something called "pass-throughs" (and just what is that)? And second, will the repair of the damaged nuclear plant make things worse?

They pay, so you pay

The term "pass-through" is what it sounds like: Certain costs that get passed through to utility customers. The utility pays, so you pay.

But that's an oversimplification. So let us explain.

Progress Energy Florida is an investor-owned company regulated by the state's Public Service Commission. The commission makes the rules and sets the rates.

There are two pieces to your electric bill, the "base rate" and "cost recovery clauses." The base rate doesn't often change. It only gets adjusted when a utility applies to the commission for a new base rate. That can be a lengthy and burdensome process, so a base rate might stay in place for years. The base rate compensates a utility for producing and delivering electricity, plus investment in its plants and facilities, plus an "allowed return" -- you might call it profit.

Again, that's the base rate. Then there are the "cost recovery clauses." Some costs -- say, for example, fuel -- rise and fall dramatically. So the commission lets a utility file a different type of request each year to pass those costs directly to you, rather than include them in its base rate. If fuel ends up costing less in a given year, ratepayers get some money back. If it costs more, well, ratepayers shell out extra. That's the essence of a pass-through.

We should note that while pass-throughs get speedier review than a proposed change to the base rate, they're not automatic. They still have to be approved by the Public Service Commission.

In Florida, fuel costs are handled as a pass-through, as are expenses related to energy efficiency programs and environmental compliance. Then there's a relatively recent, and controversial, pass-through -- for new nuclear power. That's the one that allows Progress Energy to charge you for planning and construction costs years before a project actually produces any energy. Right now, a little less than 5 percent of a typical Progress Energy residential bill helps pay for a Levy County plant that may be more than a decade away, plus a project to boost capacity at the Crystal River plant that's offline for unrelated repairs. (The Crystal River nuclear plant is the one that prompted Fasano's comments germane to this fact-check.)

In coming years, that chunk could soar dramatically.

Percentages

To test Fasano's claim that "just a little over 60 percent of your electric bill ... is pass-throughs," we asked Progress Energy Florida for a breakdown. Spokeswoman Suzanne Grant provided these numbers, which show that fuel costs make up the biggest chunk of a typical 1,000 kilowatt-hour residential bill, followed by the base rate that pays for essentials from power lines to energy workers: 
 

Description Current Change (proposed) Proposed January 2012 Base rate $48.58 $0 $48.58 Nuclear cost recovery $5.53 -$0.85 $4.68 Energy conservation cost recovery $2.99 -$0.11 $2.88 Environmental cost recovery $4.91 $0.92 $5.83 Fuel and capacity cost recovery $54.35 $5.99 $60.34 Subtotal $116.36 $5.95 $122.31 Gross receipts tax $2.98 $0.16 $3.14 Total $119.34 $6.11 $125.45

 

Featured Fact-check

We did some math, which showed that Fasano's close when he says "just a little over 60 percent." Right now, pass-throughs make up just under 60 percent, though it may be headed up:
 

  Current Proposed January 2012   Base rate 40.7 percent 38.7 percent   Cost recovery clauses (pass-throughs) 56.8 percent 58.8 percent   Gross receipts tax 2.5 percent 2.5 percent  

 

Crystal River's impact on your bill

Now, back to that Crystal River plant, which suffered cracks in its containment wall in 2009 during an attempt to replace steam generators. It's been out for the count ever since.

Some of the costs associated with the plant shutdown are pass-throughs -- more costly fuel. Progress has had to turn to more expensive sources to replace the nuclear power, such as natural gas, boosting the typical residential bill by $3.82, according to the company.

Next year, the Crystal River outage could add $4.70 a month -- again, because replacement fuel costs more than nuclear power -- meaning your bill could be nearly 4 percent higher than it would have been. 

The hit would be worse, but Progress Energy's insurance coverage has picked up quite a bit. Still, the future's not exciting: The company's coverage for replacement power expires in August 2012, according the public counsel's office, more than a year before the nuclear plant's fixed.

St. Petersburg Times reporter Ivan Penn wrote that "the utility has projected there will be an additional $1 billion in replacement power and fuel costs until the plant comes back online, with customers paying about $560 million of that cost."

Meanwhile, some of the price tag -- for the physical repairs to the plant itself -- isn't a pass-through, according to the Public Service Commission. So you won't see it for a while. If Progress wants its customers to pay for what's not covered by insurance, that would have to be part of a change to the base rate. And Progress' current agreement with the commission means no base rate update through the end of 2012.

Our ruling

Fasano said, "Already, just a little over 60 percent of your electric bill, my electric bill, 60 percent of that is pass-throughs, whether they be for building of nuclear plants or whatever they may be. This (repair) will only increase that percentage."

Pass-throughs actually represent just under 60 percent of a Progress Energy bill, so he's close.

But there's two caveats to Fasano's claim. The first is just what constitutes a pass-through. A casual reader of Fasano's statement might imagine that the bulk of a customer's bill goes to big projects unrelated to the power they consume, rather than to something as central as fuel -- and fuel represents by far the largest pass-through cost.

Second, the problems with the Crystal River plant create some pass-through costs -- through paying for more expensive fuel -- and possibly some non-pass-through costs, namely the physical repairs.

On balance, we rate Fasano's statement Mostly True.

Our Sources

St. Petersburg Times, "Progress Energy insists approach to bungled nuclear project was 'reasonable,' " Oct. 11, 2011

St. Petersburg Times, "Cleaning up a DIY repair on Crystal River nuclear plant could cost $2.5 billion," Oct. 9. 2011

St. Petersburg Times, "Progress Energy's plan for oft-delayed Levy County nuclear plant under fire," Aug. 14, 2011

St. Petersburg Times, "Progress Energy customers could soon pay much more for Levy County nuclear plant," Aug. 5, 2011

Interviews with Sen. Mike Fasano, R-New Port Richey, Oct. 11-13, 2011

Florida Public Service Commission, "Report to the Legislature On Utility Revenue Decoupling," December 2008

Interviews with Suzanne Grant, spokeswoman for Progress Energy Florida, Oct. 11-12, 2011

E-mail interview with Bev DeMello, spokeswoman for the Public Service Commission, Oct. 12, 2011

E-mail interview with Dan Riedinger, spokesman for Edison Electric Institute, the association of shareholder-owned electric companies, Oct. 11, 2011

Interview with Scott Hempling, former executive director of the National Regulatory Research Institute, Oct. 11, 2011

Interview with Charles Rehwinkel, deputy public counsel in Florida's Office of Public Counsel, Oct. 11, 2011

Browse the Truth-O-Meter

More by Becky Bowers

Sen. Mike Fasano says most of your Progress Energy Florida power bill is pass-throughs

Support independent fact-checking.
Become a member!

In a world of wild talk and fake news, help us stand up for the facts.

Sign me up