Get PolitiFact in your inbox.

By Willoughby Mariano May 23, 2012

Airport spokesman says new international terminal "within budget"

The Maynard H. Jackson Jr. International Terminal at Hartsfield-Jackson International Airport finally opened its doors after more than a decade of delays, lawsuits and changes of plans.

Local leaders are celebrating the hard-fought victory by patting each other -- and themselves -- on the back.

Atlanta Department of Aviation spokesman John Kennedy touted the city’s accomplishment during an interview with radio host Scott Slade on AM 750 and 95.5FM News/Talk WSB

"John, a lot of people have been waiting a long time to get the Maynard H. Jackson International Terminal open. Are we on time to get it open on Wednesday?" Slade asked.

"Yes indeed. It will open on time and within budget on Wednesday, May 16, and we are excited, too," Kennedy said.

Sure it opened Wednesday. But on budget? Even with all the delays?

Other officials have made similar claims. We asked Kennedy for proof.

PolitiFact Georgia also burrowed deep into The Atlanta Journal-Constitution’s archives, where we uncovered a tale of dreams deferred and plans gone awry. 

Planning for the international terminal began in earnest more than a decade ago. Leaders envisioned a crescent-shaped terminal that would double the size of the international complex to 3 million square feet.


The goal was to keep Hartsfield-Jackson competitive and improve its design. International passengers complained that they had to claim their baggage, carry it through U.S. Customs, recheck it and pick it up again. The trek covered more than a mile.


Stories printed in November 2000 pegged the cost at $719 million, including additional parking, a taxiway and road upgrades. Leaders said it could be finished as early as 2004.


Then things got complicated. Construction prices rose, and after the terror attacks of Sept. 11, 2001, so did the cost of security measures. Delta Air Lines went into bankruptcy, and leaders wondered whether the airport needed a new international terminal at all.


The airport’s original design team was fired because the then-general manager of the airport, Ben DeCosta, said its plans would break the proposed $700 million budget. The team sued the city for $60 million.


A yearlong audit that ended in May 2006 concluded that at an estimated cost of $1 billion, the international terminal was over budget.

 

That number was low.


In June 2007, the AJC obtained a copy of an internal briefing that showed that delays, design changes and rising construction costs could push the price tag as high as $1.5 billion. It would also be 400,000 square feet smaller than originally planned.


At the time, airport officials also downplayed the $1.5 billion as a "preliminary" figure and said no final budget figure had been approved. But five months later, DeCosta confirmed to the Atlanta City Council that the number was well-researched and accurate.


"The number has a lot of information behind it," DeCosta said, according to an AJC story Nov. 2007. "There are things that could push it higher, but this is close."


DeCosta also downplayed significance of the earlier $700 million budget figure. Its purpose was to establish what share of construction costs the airlines would pay, he said.

Featured Fact-check


"They weren’t original cost estimates," DeCosta said. "There was no design at that point. They were just budget numbers."


Regardless, the airport’s biggest airline, Delta, grew concerned. It is helping to pay for the new terminal, and by 2009, it worried that the ballooning price might double the airline's costs to board passengers at its main hub.

The airline wanted the terminal’s costs trimmed by $400 million, the AJC reported. 

The latest tally: About $1.4 billion, just about what the 2007 internal briefing foretold. Final numbers will be available later in the year.  


This is nearly twice the $700 million floated 10 years ago. How does this count as "within budget"?


Kennedy said he was talking about the formal budget, not the numbers from a decade ago. He sent us a budget document from May 13 of this year that placed the formal budget at $1.413 billion.


The latest projected cost was $1.403 billion, which would mean that the terminal was about $10 million under budget. He noted that other city officials have used this number before.


So what was that $700 million about? It wasn't a budget, Kennedy told PolitiFact Georgia in an email. It was a "preliminary concept estimate."


"The $700 million ... was never a budgeted number -- it was merely a preliminary concept estimate made in the late 1990s for a proposed, future east side international terminal which, together with several other major airport projects, eventually became part the Airport's Master Plan of 2000," he wrote. "There were never any detailed planning or design documents produced for this concept."


The Atlanta City Council and airlines did not formally approve a budget for the international terminal until March 2008, Kennedy said. By then, the design and other planning were complete.


Kennedy added that the original $700 million figure was not up for discussion during the radio interview, and to take that figure into account in this story would be to take his comment out of context.


This explanation made us groan.


The distinction between a "preliminary concept estimate" and a "budgeted number" is important to technocrats. But when top leaders say in public that they expect an airport terminal to cost $700 million, taxpayers expect it to cost $700 million.


Furthermore, the $700 million figure was crucial to the very people who planned the terminal. Former airport head DeCosta fired the airport's first design team, and Delta balked at backing the project when costs threatened to rise above this mark.


Kennedy's claim that the airport terminal is "within budget" goes down in flames.


Pants on Fire.

Our Sources

Email interview, John Kennedy, senior public relations manager, Atlanta Department of Aviation, May 18, 2012


The Atlanta Journal-Constitution, "Atlanta's new terminal in limbo," Feb. 1, 2009


The Atlanta Journal-Constitution, "Airport project doubles in cost," Nov. 5, 2007


The Atlanta Journal-Constitution, "Now departing: Good estimates," July 8, 2007


The Atlanta Journal-Constitution, "File: Costs soar, terminal shrinks," June 21, 2007


The Atlanta Journal-Constitution, "Hartsfield City Limits: Site chosen for new east terminal," Nov. 6, 2000


The Atlanta Journal-Constitution, "Airport plan seen as boon to Gateway," Nov. 9, 2000

Browse the Truth-O-Meter

More by Willoughby Mariano

Airport spokesman says new international terminal "within budget"

Support independent fact-checking.
Become a member!

In a world of wild talk and fake news, help us stand up for the facts.

Sign me up